1月8日 Coordinate Project Server and Windows SharePoint Services securityProject Server 2007 did some improvement on WSS integration (If you want to know about integration between project server 2003 and WSS 2.0, please see my post:Customize WSS Role/User permission for Project Server 2003). You may read Microsoft TechNet article about this: http://technet2.microsoft.com/Office/en-us/library/c9ca0b66-c167-4cd1-8ecf-6b311cf6976a1033.mspx?mfr=true.
Project Server 2007 is completed built on the top of WSS 3.0. It will create four SharePoint groups on every project workspace:
Normally user would not be in two groups at same time, except team members and readers. User could be in team members and readers groups if users assigned to tasks and have view project workspace permission on my organization category.
By default, WSS security settings will change according to PWA security changes. However, you can change the settings on the Project Workspace Provisioning Settings page to check the box "Automatically add Project Web Access users to project team Web site when SharePoint site is created or when the project manager publishes the project information to Project Server"
Then, what scenarios will change the WSS security?
Since the first three scenarios may affect large number of project workspace, the best practice is to create/change those resources during non-working hours.
Microsoft documents that denying Logon permission and View Project Workspace will affect WSS security. However, as I tested, I did not find denying those permission will affect WSS. Use PSI event to validate timesheetIn project server 2007, timesheet is a very good new feature. However, when user enters timesheet and save it back to server, the server does not validate the number. For example, user can enter 30 hours for a day. You can set the limitation in Timesheet settings, however project server only validate timesheet hours when user submits it. What if you don't want team members to enter ridiculous hours, here is a solution. You can use PSI event handler to track the changes and cancel the change for whatever reason. Here is how to do it. Step 1: create a project server event handler to validate user input. Timesheet Updating event occurs when a user tries to save timesheet but before it is actually saved. You can use this event to validate user input. If the timesheet is valid, you will let timesheet being saved. Otherwise you can cancel the process and abort saving. You can use Timesheet web service to find the hours saved before. And you can find what user changed in the TimesheetPreUpdateArgs class, which is stored in DsDelta dataset. DsDelta dataset would only store the changed hours not all hours. You need to merge the two dataset to get “real” updating dataset. If you find the hours are not valid, you can set the TimesheetPreUpdateEventArgs.Cancel=True and TimesheetPreUpdateEventArgs.CancelReason=”Timesheet cancel reson”. Then project server will stop processing timesheet updating and return to timesheet page. Project server will also save an error message to event log. However, when you return to timesheet page, the project server does not show any message for cancelling timesheet. You will need the second step to show the actual reason. Here is some sample code that it can check if actual hours in one day is more than 24 hours. If so, it will cancel the event. public override void OnUpdating(PSContextInfo contextInfo, TimesheetPreUpdateEventArgs e) { if (e.DsDelta == null) { return; }
TimesheetSvc.TimeSheet ts = new TimesheetSvc.TimeSheet(); ts.Url = _EPMSite + _TimesheetSvc; ts.Credentials = CredentialCache.DefaultCredentials; TimesheetSvc.TimesheetDataSet tsDs = ts.ReadTimesheet(e.TsUID);
TimesheetSvc.TimesheetDataSet.ActualsDataTable tblActuals = MergeActuals(tsDs.Actuals, e.DsDelta.Actuals);
Dictionary<DateTime, Decimal> TblTotal = AccumulateActuals(tblActuals);
string Msg = ValidateActuals(TblTotal); if (Msg != "") { e.CancelEvent(Msg); } }
Step 2: create a custom web part to show cancel reason.
Since the timesheet page cannot show cancel reason from event handler, you may need to create a custom web part to show the reason. You can just create a very simple web part which contains a label control. The web part will read event log and display if it found any recent error log. Add More Time Hierarchy in Project Server 2007 CubesMany organizations have their own definitions of time. Project Server standard time dimension may not fit their needs. Don't worry, we can extend the cube by adding more time hierarchies.
In Analysis Service 2005, one dimension could have multiply hierarchies. Now we don't need to add time dimension but just add another time hierarchy. If you want to find information about adding time dimension in project server 2000, you may check another post: http://netsleeper.spaces.live.com/blog/cns!2D6B305EBBD50AA5!127.entry
Another good thing in project server 2005 is that we can use event and managed code. We can write code on OnCubeProcessed event. This event occurs after project server processed OLAP cube. Since we are creating time hierarchy, we need to wait project server finishing creating time dimension.
Here, I am using Analysis Management Object API for Analysis Service 2005, which is similiar but a little different from old way. The following sample code is to create another time hierarchy that only have year, week and day. So that week will not split between months.
public override void OnCubeProcessed(PSContextInfo contextInfo, CubeAdminPostCubeProcessEventArgs e)
{ try
{ WriteMessage("Start Cube Extension"); // connect analysis service server
Server OLAPServer = new Server(); OLAPServer.Connect("Data Source=" + e.ServerName + ";Provider=msolap;"); WriteMessage("Analysis service server connected:" + e.ServerName); // open EPM OLAP database Database EPMOLAP = OLAPServer.Databases.FindByName(e.DbName); if (EPMOLAP == null) { EventLog.WriteEntry(LogSource, "Database: " + e.DbName + " does not exist in Project Server 2007 cube.", EventLogEntryType.Error); return; } WriteMessage("Start building new Time hirarchy");
// open Time dimension
Dimension dmnTime = EPMOLAP.Dimensions[TimeDimensionID]; if (dmnTime == null)
{ EventLog.WriteEntry(LogSource, "Time dimension does not exist.", EventLogEntryType.Error); return; } // check if the custom hierarchy is already created
if (dmnTime.Hierarchies.FindByName(NewTimeDimensionName) != null) { EventLog.WriteEntry(LogSource, "New Time hierarchy has already been created by other process.", EventLogEntryType.Error); return; } // create custom hierarchy in time dimension
Hierarchy NewTime = dmnTime.Hierarchies.Add(NewTimeDimensionName); // find year, week, and day attribute in time dimension
DimensionAttribute atrYear = dmnTime.Attributes.FindByName(YearAttributeName); if (atrYear == null) { EventLog.WriteEntry(LogSource, "Year attribute does not exist in Time dimension.", EventLogEntryType.Error); return; } DimensionAttribute atrWeek = dmnTime.Attributes.FindByName(WeekAttributeName); if (atrWeek == null) { EventLog.WriteEntry(LogSource, "Week attribute does not exist in Time dimension.", EventLogEntryType.Error); return; } DimensionAttribute atrDay = dmnTime.Attributes.FindByName(DayAttributeName); if (atrDay == null) { EventLog.WriteEntry(LogSource, "Day attribute does not exist in Time dimension.", EventLogEntryType.Error); return; } // create level for year, week, and day in custom hierarchy
Level lvlYear = PPGTime.Levels.Add(YearLevelName); lvlYear.SourceAttributeID = atrYear.ID; Level lvlWeek = PPGTime.Levels.Add(WeekLevelName); lvlWeek.SourceAttributeID = atrWeek.ID; Level lvlDay = PPGTime.Levels.Add(DayLevelName); lvlDay.SourceAttributeID = atrDay.ID; WriteMessage("Complete building hirarchy"); // save the changes to database. dmnTime.Update(); WriteMessage("Complete Cube Extension"); } catch (Exception ex) { EventLog.WriteEntry(LogSource, ex.ToString(), EventLogEntryType.Error); } } |
|
|